Assigns, removes, or replaces the resources of the selected tasks, or changes the number of units for a resource.
expression.ResourceAssignment (Resources, Operation, With)
expression A variable that represents an Application object.
Name | Required/Optional | Data type | Description |
---|---|---|---|
Resources | Optional | String | The names of the resources to be assigned, removed, or replaced in the selected tasks. Note Project will not assign a resource if thousands separators or decimal separators are included in the unit values. |
Operation | Optional | Long | If Operation is omitted, Project assigns the resources to the selected tasks. The default value is pjAssign. Can be one of the PjResAssignOperation constants. |
With | Optional | String | When used with the pjReplace constant for Operation, specifies the names of the resources that replace the resources of the selected tasks. |
Constant | Description |
---|---|
pjAssign | Assigns the specified resources to the selected tasks. |
pjRemove | Removes the specified resources from the selected tasks. |
pjReplace | The resources specified by With replace the resources specified by Resources. |
pjChange | Changes the resource units for the specified resource. This constant can be used only for a single resource. |
Boolean
Use the Resources parameter to specify that a resource assignment is requested or demanded when using the Resource Substitution Wizard. For example, the following macro specifies that the assignment of r1 to the selected task is a requested assignment.
Sub RequestAssignment()
ResourceAssignment Resources:="r1[100%, R]", Operation:=pjChange, With:=""
End Sub
Note
When using the Resources parameter in this way, D specifies "Demand," R specifies "Request," and N specifies "None." In addition, spaces are not allowed between the units value and the Request/Demand value. For example, Resources:="100%,R"
works, but Resources:="100%, R"
does not.
The Resource Substitution Wizard cannot substitute material resources. Therefore, you cannot request or demand a material resource for a particular assignment by using the Resources parameter.
The following example prompts the user for the name of a resource, and then assigns that resource to the selected tasks.
Sub AssignResourceToSelectedTasks()
Dim Entry As String ' The name of the resource to add to selected tasks
Dim R As Resource ' Resource object used in For Each...Next loop
Dim Found As Boolean ' Whether or not the resource is in the active project
Entry = InputBox$("Enter the name of the resource you want to add to the selected tasks.")
' Assume resource doesn't exist in the active project.
Found = False
' Look for the resource.
For Each R In ActiveProject.Resources
If Entry = R.Name Then Found = True
Next R
' If the resource is found, then assign it to selected tasks.
If Found Then
ResourceAssignment Resources:=Entry, Operation:=pjAssign
' Otherwise, tell user the resource doesn't exist.
Else
MsgBox ("There is no resource in the active project named " & Entry & ".")
End If
End Sub