Gets a Shift object representing the first work shift in a day. Read-only Shift.
expression. Shift1
expression A variable that represents a Day object.
The following example schedules a half-day of work on Fridays by creating an 8 A.M. to noon shift.
Sub HalfDayFridays()
With ActiveProject.Calendar.WeekDays(pjFriday)
.Shift1.Start = #8:00:00 AM#
.Shift1.Finish = #12:00:00 PM#
.Shift2.Clear
.Shift3.Clear
End With
End Sub