Project.MoveCompleted property (Project) |
vbapj.chm131106 |
|
project-server |
|
83ecef23-b57b-3b7e-2563-6e26a14f18f5 |
06/08/2017 |
medium |
True if a task that is scheduled after the status date has actual progress entered against it and the actual, completed portion of the task is moved so the completed work ends on the status date. Read/write Boolean.
expression. MoveCompleted
expression A variable that represents a Project object.