Gets the VAC (Variance At Completion) cost for the resource. Read-only Variant.
expression. VAC
expression A variable that represents a Resource object.
The VAC shows the difference between the baseline cost (the BAC or Budgeted At Completion) and the EAC (Estimated At Completion).