WeekDay.Shift2 property (Project)

Gets a Shift object representing the second work shift in a weekday. Read-only Shift.

Syntax

expression. Shift2

expression A variable that represents a WeekDay object.

Example

The following example schedules a half-day of work on Fridays by creating an 8 A.M. to noon shift.

Sub HalfDayFridays() 
 
 With ActiveProject.Calendar.WeekDays(pjFriday) 
 .Shift1.Start = #8:00:00 AM# 
 .Shift1.Finish = #12:00:00 PM# 
 .Shift2.Clear 
 .Shift3.Clear 
 End With 
 
End Sub