title | ms.service | api_name | ms.assetid | ms.date | ms.localizationpriority | |
---|---|---|---|---|---|---|
Year.Shift4 property (Project) |
project-server |
|
4a4b8e9e-713f-a38c-f4f7-d93b47e72e8b |
06/08/2017 |
medium |
Gets a Shift object representing the fourth work shift throughout a year. Read-only Shift.
expression. Shift4
expression A variable that represents a Year object.
The following example schedules a half-day of work on Fridays by creating an 8 A.M. to noon shift.
Sub HalfDayFridays()
With ActiveProject.Calendar.WeekDays(pjFriday)
.Shift1.Start = #8:00:00 AM#
.Shift1.Finish = #12:00:00 PM#
.Shift2.Clear
.Shift3.Clear
End With
End Sub