Full ADCS implementation (uncalibrated)

Due by March 01, 2025 70% complete
  • Completion of sun acquisition module: pyramid sun sensor integration
  • Sun vector HW validation with external set-up
  • MCM unit testing for voltage allocator and controller
  • Optimized MEKF (AD) implementation and associated fault handling
  • SIL validation from initial tumble rate to sun-pointed operations
  • Completion of sun acquisition module: pyramid sun sensor integration
  • Sun vector HW validation with external set-up
  • MCM unit testing for voltage allocator and controller
  • Optimized MEKF (AD) implementation and associated fault handling
  • SIL validation from initial tumble rate to sun-pointed operations